Applications, viable projects, construction and connection — NESO’s real connections register, the historic 700+ GW headline, and the 2025 reform that is trying to fix it.

Before reform, after reform, and today

The 283 GW "retained pipeline" figure is NESO’s own reform-adjusted total (published 8 December 2025) — it is not derived by summing the public TEC Register (which still totals ~735 GW because the register itself has not been purged of legacy Scoping-stage applications). Treat the 700 GW+ and 283 GW figures as answering two different questions — "everything that has ever applied" vs "what NESO now expects to actually connect" — not as two measurements of the same thing.

Before reform

700+ GW

More than 700 GW of generation and storage projects waiting for grid access

Widely cited through 2024–25 (the "queue crisis" headline); still visible today as the raw total of NESO’s public connections register

After reform — retained pipeline

283 GW

132 GW aligned to the 2030 Clean Power target + 151 GW for 2035 system needs

8 December 2025

Raw register today

735 GW

2,200 projects in the live TEC Register — NOT purged of legacy speculative applications

As at 25 August 2026

More than 300 GW of old-queue projects will not move forward under the reformed process.

Supply is not the whole queue — demand connections are separate

The ~100 GW transmission-connected demand figure and the 283 GW generation/storage figure answer different questions (what the grid will supply vs what it will be asked to serve) and are never added together on this site.

Transmission-connected demand

~100 GW

New or expanded demand connections — data centres, electrolysers, industrial loads — identified separately from the 283 GW generation/storage pipeline above.

Already connected

~111 GW

Existing generation and storage already connected to the transmission network — the baseline the 283 GW pipeline builds on top of, not part of it.

Source: NESO, 8 December 2025press release.

Connections Reform timeline

15 Apr 2025
Ofgem approves NESO’s TMO4+ connections reform ("first ready, first connected")source
10 Jun 2025
Connections Reform goes live; NESO reports an interim retained pipeline of 238 GW (217 GW moved to Gate 1)source
21 Nov 2025
Gate classification field added to the public TEC Registersource
8 Dec 2025
NESO publishes the finalised retained/prioritised pipeline: 283 GWsource

The retained pipeline by technology (2030-aligned)

34.5 GW

Battery storage

32.1 GW

Offshore wind

29.9 GW

Solar

13.1 GW

Onshore wind

11.8 GW

Transmission-connected demand

3.3 GW

Nuclear

3.3 GW

Low-carbon dispatchable (e.g. gas + CCS, hydrogen)

Retained pipeline aligned to Clean Power 2030, by technology

Battery storage, offshore wind and solar make up the bulk of the 2030-aligned pipeline. Nuclear and low-carbon dispatchable generation are a small fraction of it — a pipeline weighted heavily towards variable and storage capacity.

View data table
Retained pipeline aligned to Clean Power 2030, by technologyGreat Britain. Source: NESO, Connections Reform outcome. 8 December 2025.
PeriodCapacity aligned to Clean Power 2030
Battery storage34.5
Offshore wind32.1
Solar29.9
Onshore wind13.1
Transmission-connected demand11.8
Nuclear3.3
Low-carbon dispatchable (e.g. gas + CCS, hydrogen)3.3

Great Britain · Source: NESO, Connections Reform outcome · as of 8 December 2025

Source: NESO, 8 December 2025press release.

Applications → viable → construction → connected

The live TEC Register's own status field, today — every project at any stage, 2,200in total. This is a genuinely different question from the before/after reform figures above: "where does everything in the register sit right now", not "what will actually get built".

Scoping (application stage)1,486 projects · 539.2 GW
Awaiting consents148 projects · 57.7 GW
Consents approved172 projects · 49.1 GW
Under construction / commissioning19 projects · 3.4 GW
Built (connected)375 projects · 85.9 GW

Status and Gate are two INDEPENDENT classifications, not stages of one funnel — a project can be "Scoping" status and already hold a Gate 1 connection agreement, or "Built" with no Gate assigned at all (verified by cross-tabulating the two columns in the real register: every combination occurs). NESO’s own dataset notes state capacity figures "may result in duplicate entries" pending further data cleaning. Transmission-connected projects only — large volumes of embedded/distribution-connected generation and demand sit in separate DNO-level registers not covered here (Scotland’s embedded generation has its own NESO "Embedded Register").

Post-reform Gate classification

Gate 1 (higher readiness)743 · 278.4 GW
Gate 2 (lower readiness)85 · 12.9 GW
Not yet gated1,372 · 444.0 GW

Gate is independent of Project Status above — a project can be at any register stage and hold, or not hold, a Gate assignment.

By transmission owner (region)

NGET (England & Wales)1,284 · 546.1 GW
SHET (North Scotland)444 · 99.4 GW
SPT (South & Central Scotland)457 · 85.6 GW
OFTO (Offshore transmission (licensed separately))15 · 4.2 GW

The register has no separate region/GSP code — HOST TO (transmission licensee) is the closest genuinely regional field it publishes.

How this is calculated, and what "evidence class" means
  • B — Official/admin statistic with methodological limitations — every figure on this page: NESO's TEC Register (an operational register, not an audited statistical release) and NESO's own reform press releases.

Every total here was computed by summing NESO's own published register directly, project by project — not transcribed by hand from a press release. The register is public, so each figure can be checked against the current version at source.