Government delivery · UK government · 12 commitments since 20 July 2026 · assessed 3 October 2026

Half the government’s tracked pledges still lack a costed timetable.

Of twelve commitments tracked since 20 July 2026, six had a date, a cost (or no spending cost) and a delivery mechanism at our latest checks (to 3 October); one of those was in force. The remaining six include care, council housing and devolution promises.

Our purpose: Track each commitment’s owner, resources, milestones and outcomes on the same tests.

Evidence last reviewed 3 October 2026

Context: Andy Burnham became Prime Minister on 20 July 2026, after Keir Starmer resigned, and leads a Labour government elected in July 2024. The 2024 manifesto commitments it inherited are tracked separately on the manifesto tracker. How the government took office · Manifesto tracker

Overview

The short version

Three key measures

Why it matters

These are the baselines the government inherited. A later change in any of them will not by itself show that a commitment worked: other policies, the economy and earlier decisions all move the same numbers. The board marks an outcome “Yes” only when a commitment has a defined measure and a published result after delivery began.

The evidence

From announced promises to delivery and public outcomes

GOV-01 · How far has the tracked programme reached?

One commitment in force; six still without a dated, costed plan

Each tracked commitment made by the government since 20 July 2026, assessed at four stages. “Not applicable” means the stage does not apply (a regulatory change has no spending to fund). Stages can run in parallel; this is not a strict sequence.

Key: Yes · Partly · Not yet · Scheduled, unconfirmed · Not applicable. Labels are written out in every cell.

One commitment in force; six still without a dated, costed plan. Rows are commitments; columns are delivery stages.
Commitment and ownerDated, costed planFunding or legal authorityReaching the publicMeasured outcome
Remove 5% VAT from domestic electricityCost of living · HM Treasury and HMRCChecked 3 October 2026 · sourceYesDated (1 October 2026 to 31 March 2027), costed at about £850m for 2026/27, delivered through a VAT order.YesThe Value Added Tax (Supplies of Domestic Electricity) Order 2026 has been made; funded for 2026/27.YesIn force from 1 October 2026 for supplies in Great Britain (not Northern Ireland).Not yetBills issued after 1 October will show it first; the October and November consumer price index releases are the first official measures. Evidence
£2 cap on single bus faresTransport · Department for TransportChecked 11 August 2026 · sourceYesDated (January 2027) and costed (£454m), delivered through funding to bus operators.YesFunding redirected from the energy department.Not yetStarts January 2027; operator agreements are not yet confirmed.Not yetBus passenger journeys and fares are the relevant measures; this site does not yet hold a transport series.
Cut business rates for pubs, clubs and music venuesBusiness & high street · HM Treasury and MHCLGChecked 11 August 2026 · sourceYesDated (April 2027) with an estimated cost (about £100m a year) and a mechanism (business-rate relief).Not yetFunding and final design are due at the Budget on 28 October 2026.Not yetWould apply to bills from April 2027.Not applicableThe outcome is the bill reduction itself; the effect on venue numbers would need separate evidence.
Council powers over vape shops and betting premisesBusiness & high street · MHCLG and DCMSChecked 11 August 2026 · sourceYesTarget date (early 2027) and a published consultation; a regulatory change with no spending cost.Not yetPlanning changes need secondary legislation; the Gambling Act change needs primary legislation.Not yetNot in force.Not applicableNo outcome measure is defined.
Crack down on misleading discounts and subscription trapsConsumer · Department for Business and TradeChecked 11 August 2026 · sourceYesTarget date (January 2027) and consultation; a regulatory change with no spending cost.Not yetRules not yet made.Not yetNot in force.Not applicableNo outcome measure is defined.
Pause and narrow the early-release schemeJustice · Ministry of JusticeChecked 3 October 2026 · sourceYesRelease changes are set in the Sentencing Act 2026 with a scheduled commencement; the exclusions narrow who is eligible.YesSentencing Act 2026.Scheduled, unconfirmedCommencement was rescheduled to October 2026; this site has not confirmed it took place.Not yetReoffending by the released cohort and prison population are the relevant measures; neither is yet published for this cohort. Evidence
A National Care ServiceSocial care · Department of Health and Social CareChecked 3 October 2026 · sourceNot yetNo delivery date, cost or eligibility system; design awaits the Casey Commission.Not yetNo funding model.Not yetNot started.Not yetDelayed hospital discharges and care-worker vacancies are the measures to watch. Evidence
End rough sleepingHousing · MHCLG, with councils and mayors deliveringChecked 3 October 2026 · sourcePartlyFirst phase costed (£340m) with outputs (1,200 homes, 3,000 people) and a locally led delivery route, but no date by which rough sleeping ends.PartlyFirst phase funded; later years of the five-year programme are not.PartlyProgramme launched; delivery led by councils and mayors.Not yetThe official rough-sleeping snapshot is the outcome measure; this site holds temporary accommodation, a related but different measure. Evidence
Build substantially more council housingHousing · MHCLG and Homes EnglandChecked 11 August 2026 · sourceNot yetNo national target, date or funding programme.Not yetNo new funding announced.Not yetNot started as a new programme.Not yetNet additional dwellings and social-rent completions are the measures. Evidence
Push power “into every postcode” and create No 10 NorthDevolution · MHCLG and HM TreasuryChecked 3 October 2026 · sourceNot yetPolicy paper only; the white paper and timetable are still to come.Not yetFiscal devolution would need legislation.Not yetNot started.Not yetNo outcome measure defined.
Reindustrialise and extend public control of essential servicesEconomy · Department for Business and Trade, HM Treasury and Cabinet OfficeChecked 11 August 2026 · sourceNot yetA 10-year plan is promised; no costings or sequencing.Not yetNone yet.Not yetProcurement measures are tracked separately on /public-procurement.Not yetBusiness investment and output per hour are the relevant measures. Evidence
Reform education and youth mental-health supportEducation · Department for Education, DHSC and DWPChecked 11 August 2026 · sourceNot yetNo programme, numbers or funding.Not yetNone yet.Not yetNot started.Not yetYoung people not in education, employment or training (NEET) is the closest measure. Evidence

The board separates four things that headlines often merge: a specified plan, the money or law that allows it, the change actually reaching the public, and a measured result. Cost-of-living measures moved fastest; the commitments with the largest likely cost have no plan yet. The selection is the government’s own headline pledges, not its whole programme, and statuses can lag announcements — each row carries the date it was checked.

Source: UK Facts commitment registry, compiled from the government announcement, policy paper or report linked on each row. Site assessment against the criteria under Sources and methods. Board GOV-01.

What changed recently?

Dated steps recorded in the registry, newest first. Announcements without a date for delivery are not listed as progress.

  1. 1 October 2026 · Remove 5% VAT from domestic electricity

    Zero rate of VAT on domestic electricity in force in Great Britain.

    HMRC policy paper
  2. 8 September 2026 · Remove 5% VAT from domestic electricity

    HMRC published the policy paper and Revenue and Customs Brief 10 (2026); the VAT order was made.

    HMRC, Revenue and Customs Brief 10 (2026)
  3. 4 August 2026 · Pause and narrow the early-release scheme

    Rape, serious child-sex and grooming offences excluded; commencement delayed from September to October 2026.

    gov.uk announcement
  4. 3 August 2026 · Push power “into every postcode” and create No 10 North

    Rewiring the State policy paper published; Budget date set for 28 October 2026.

    Civil Service World
  5. 29 July 2026 · A National Care Service

    Casey Commission phases merged into one report, brought forward to summer 2027.

    Prime Minister’s speech on social care

What does each commitment cost, and who pays?

Costs are as the government stated them; none is yet certified by the Office for Budget Responsibility, which scores measures at fiscal events. The next is the Budget on 28 October 2026.

CommitmentStated cost and funding sourceFunding or legal authority
Remove 5% VAT from domestic electricityEstimated at £850m in 2026/27 when announced, funded this year by cancelling the Digital ID programme. HMRC’s policy paper says the final costing will be scrutinised by the OBR and set out at a future fiscal event.Yes. The Value Added Tax (Supplies of Domestic Electricity) Order 2026 has been made; funded for 2026/27.
£2 cap on single bus fares£454m redirected from the energy department.Yes. Funding redirected from the energy department.
Cut business rates for pubs, clubs and music venuesPackage estimated at roughly £100m a year; final costing due at the Budget on 28 October 2026.Not yet. Funding and final design are due at the Budget on 28 October 2026.
Council powers over vape shops and betting premisesNo spending cost (regulatory)Not yet. Planning changes need secondary legislation; the Gambling Act change needs primary legislation.
Crack down on misleading discounts and subscription trapsNo spending cost (regulatory)Not yet. Rules not yet made.
Pause and narrow the early-release schemeNo spending cost (regulatory)Yes. Sentencing Act 2026.
A National Care ServiceNo cost or funding source statedNot yet. No funding model.
End rough sleeping£340m additional funding announced on 20 July 2026, described as the opening investment in a five-year programme.Partly. First phase funded; later years of the five-year programme are not.
Build substantially more council housingNo cost or funding source statedNot yet. No new funding announced.
Push power “into every postcode” and create No 10 NorthNo cost or funding source statedNot yet. Fiscal devolution would need legislation.
Reindustrialise and extend public control of essential servicesNo cost or funding source statedNot yet. None yet.
Reform education and youth mental-health supportNo cost or funding source statedNot yet. None yet.

GOV-02 · What changed for the public?

Too soon to see: the latest official outcomes mostly pre-date this government

What happens next?

The next dated step for each commitment that has one. 4 commitments have no dated next step: end rough sleeping; build substantially more council housing; reindustrialise and extend public control of essential services; reform education and youth mental-health support.

WhenCommitmentMilestoneOwner
October 2026Pause and narrow the early-release schemeRescheduled commencement of the revised release rulesMinistry of Justice
28 October 2026Cut business rates for pubs, clubs and music venuesFinal design and costing at the BudgetHM Treasury and MHCLG
28 October 2026Push power “into every postcode” and create No 10 NorthBudget promised to “move money and power out of Westminster”MHCLG and HM Treasury
January 2027£2 cap on single bus fares£2 single-fare cap due to startDepartment for Transport
January 2027Crack down on misleading discounts and subscription trapsSubscription rules targetedDepartment for Business and Trade
Early 2027Council powers over vape shops and betting premisesPlanning and licensing changes targetedMHCLG and DCMS
31 March 2027Remove 5% VAT from domestic electricityTemporary zero rate ends unless extended; costing due at a fiscal eventHM Treasury and HMRC
Summer 2027A National Care ServiceCasey Commission single report dueDepartment of Health and Social Care

12 commitments tracked; 3 have funding or legal authority in place.

Shareable visual summary

Visual summary

Image held

The image is not offered for download or sharing until the reasons below are resolved. The chart here is drawn from today’s records.

Half the government’s tracked pledges still lack a costed timetable.

Of twelve commitments tracked since 20 July 2026, six had a date, a cost (or no spending cost) and a delivery mechanism at our latest checks (to 3 October); one of those was in force. The remaining six include care, council housing and devolution promises. UK Facts’ own tracker classification of selected commitments since 20 July 2026 — not all government policy. A missing plan is not a broken deadline.

  • 12commitments tracked since 20 July 2026
  • 6with a date, cost and mechanism
  • 6without one yet
  • 1rule or policy in force

Site tracker classification, not an official statistic.

From promise to result

  1. Step 1ProposalStated intention
  2. Step 2Costed planDate and funding
  3. Step 3DeliveryIn force, money spent
  4. Step 4Measured resultIndependent outcome data

Why the supplied image is held

  • Prints TWO … A DATE AND FUNDING; the current record is 6 for Since 20 July 2026 (Commitments with a dated, costed delivery plan)
  • The image uses an earlier four-way classification of the tracked pledges that the current tracker no longer uses.
Text and data version

Half the government’s tracked pledges still lack a costed timetable. Of twelve commitments tracked since 20 July 2026, six had a date, a cost (or no spending cost) and a delivery mechanism at our latest checks (to 3 October); one of those was in force. The remaining six include care, council housing and devolution promises. UK Facts’ own tracker classification of selected commitments since 20 July 2026 — not all government policy. A missing plan is not a broken deadline.

Records behind this visual summary
MeasureValuePeriodGeographyTypeSource
Commitments tracked12Since 20 July 2026United Kingdomsite tracker classification (site record)UK Facts government delivery tracker
Commitments with a dated, costed delivery plan6Since 20 July 2026United Kingdomsite tracker classification (site record)UK Facts government delivery tracker
Commitments without a dated, costed delivery plan6Since 20 July 2026United Kingdomsite tracker classification (site record)UK Facts government delivery tracker
Commitments with the rule or policy in force1Since 20 July 2026United Kingdomsite tracker classification (site record)UK Facts government delivery tracker

All visual summaries, their source records and their publication state are listed on Shareable visuals.

Go deeper

Evidence → choices → outcomes

What could improve it?

Every government commitment moves from a credible, published plan — owner, budget, milestones and a matching measure — to a result the public can check.

These options link to their national assessment, including funding, delivery constraints and remaining uncertainties.

  • Assessed option · provisional

    Deliver what is already funded

    8/10 criteria scored

    Coverage of the appraisal, not an impact score.

    Delivery: Amber

    Whole-life costs incomplete

    Evidence and delivery constraints

    Audits diagnose failures; no general cash saving is established for this proposal.

    Name contracts, renewal dates and weaknesses; recruit commercial expertise; publish baselines, performance and remedies.

This domain in the UK SWOT →UK National Action Plan →

How we assessed these options

What would it take to improve this?

What would move the needle?

The outcome we want: Every government commitment moves from a credible, published plan — owner, budget, milestones and a matching measure — to a result the public can check.

The main constraint: Departments have not published delivery plans since 2021 and several commitments still await money at the Budget or legislation, so whether a commitment can be judged depends on Cabinet Office, Treasury and departmental decisions to publish plans and on funding and legal authority, not on reporting alone.

Constraint type: coordination, money, legislation.

The options on the table

What is funded now, and the changes assessed against it — the current baseline and the alternatives, before the position today and the actions.

Provisional single-reviewer assessments from the 6 October 2026 review; not approved business cases, and not government policy.

Assessed with another page as home

These options also bear on this topic. The full assessment sits on the home page named under each.

  • Deliver what is already fundedDelivery RAG: Amber

    Home: Follow the money.

    Funded now
    Not yet stated in the record.
    The change assessed
    Not yet defined.

    Range if completed: 14.0–20.0 out of 30 (equal weights; not yet assessed: expected incremental benefit (Bn), incremental affordability (Co))

  • Make council and SEND funding risks explicit before promises expandDelivery RAG: Amber

    Home: SEND.

    Funded now
    Not yet stated in the record.
    The change assessed
    Build a service-duty, demand, reserves and workforce baseline for exposed councils; appraise settlement choices explicitly.

    Range if completed: 16.0–22.0 out of 30 (equal weights; not yet assessed: expected incremental benefit (Bn), incremental affordability (Co))

Alternatives already on record: 15 options listed under the points in the position today (8 without an action record), and 3 earlier options under other options compared. They have not been scored in the review.

The position today

  • What we can build on (2)
  • What is holding us back (2)Our dated assessment finds 6 of 12 tracked commitments without a date, cost and delivery mechanism, and 0 of 12 with a measured result — a plan is not an outcome.
  • What could improve things (1)Publishing an owner, budget, milestones and a matching measure for each commitment — as the NAO recommends for departmental plans — would let delivery be judged against the plan rather than the announcement.
  • What could make it worse (1)

Which quadrant a point sits in is our analytical judgement, not a statistical category. Each point says whether it is a measured fact, our synthesis or a risk.

What we can build on Strengths

  • This site’s delivery board already separates four stages for each of 12 commitments made since 20 July 2026 — plan, money or law, delivery and measured outcome — each linked to its government source and dated.

    Our synthesisConfidence: Moderate

    Source: Prime Minister’s Office (gov.uk), First speech as Prime Minister (20 July 2026)

    What government has committed to

    No commitment found. No government commitment to publish a stage-by-stage tracker of the Prime Minister’s own pledges was found. The closest are the annual departmental Strategic Plans promised in November 2025 (not found for 2026-27) and the streamlined outcomes framework for mayors promised in July 2026.

    Searched: gov.uk search API (policy papers, speeches, press releases since 20 July 2026), the Plan for Change and planning and performance framework, 4 Oct 2026

    Checked 4 October 2026. A commitment is not delivery.

    Options (2)
  • Government has done this before: departments produced outcome delivery plans with priorities, metrics and resources after the 2020 Spending Review, and still use them internally.

    Measured factConfidence: High· Plans produced 2020–21· UK central government

    Source: National Audit Office, Lessons learned: a planning and spending framework that enables long-term value for money (HC 234, Session 2024-25) (Paragraphs 1.17 and 2.16 (printed pp.18, 26))

    What government has committed to

    Policy: Departmental Outcome Delivery Plans, with priority outcomes, strategies and metrics, were published in July 2021 after the 2020 Spending Review.

    Who and when:
    Earlier UK government (before July 2024), 15 July 2021.
    Since 20 July 2026:
    Not confirmed either way since the change of Prime Minister on 20 July 2026. Replaced in the November 2025 framework by departmental Strategic Plans (Starmer government); no Burnham-era statement on either was found.

    Checked 4 October 2026. A commitment is not delivery.

    Options (2)

What is holding us back Weaknesses

What could improve things Opportunities

What could make it worse Threats

The actions worth examining

These actions concern transparency, accountability and informed choice — not a spending programme, and not a view on which party or system is right.

  1. Give every commitment an owner, budget and measurable result — not a direct public-spending programme
  2. Tie spending decisions to realistic outcomes and costs — not yet costed / funding not identified
  • Action 1A37Policy status: external proposal

    Give every commitment an owner, budget and measurable result

    Departments publish dated delivery plans with baselines, milestones and spending for each commitment, keep the original promise and every revision, and explain slippage — so progress is judged against a plan rather than a speech.

    Assessment (draft, 6 October review)

    Not assessed in the 6 October review; this action stays in the topic plan with its own evidence.

    Who decides:
    Cabinet Office and HM Treasury, with each responsible department; Parliament scrutinises (UK)
    Evidence:
    Expert or audit recommendation. An independent audit recommendation drawn from NAO value-for-money work; no evaluation shows that published plans improve delivery.
    Expected effect:
    Direction plausible; size not established.
    Cost and funding

    Not yet costed

    Funding: Not a direct public-spending programme

    Why it is shortlisted here: Directly fills the gaps the delivery board shows: missing owner, cost, milestone and measure.

    What it takes
    The problem

    Half the commitments tracked on this site lack a dated, costed plan, and departments have not published outcome delivery plans since July 2021, so delivery is hard to judge against what was promised.

    Who is affected, and where

    Voters, Parliament and the people who use the services each commitment affects. Territory: UK. UK government departments; many commitments apply to England only. Devolved governments publish their own programmes and are not covered here.

    Policy status

    Proposed by researchers or others, not government policy. Recommended by the National Audit Office (October 2024). Outcome delivery plans were produced after the 2020 Spending Review and published in July 2021, but not since; ministers told a Commons committee in 2023 that they were used internally. UK Facts’ own registry tracks plan, authority, delivery and outcome for each tracked commitment — a site-editorial complement, not a substitute.

    The evidence
    What the research found:
    The NAO recommends publishing departmental outcome delivery plans and cross-cutting mission plans at least annually, plus a summary of spending choices after each spending review. It finds government “prone to under-estimate on costs and over-promise on outcomes”.
    Evaluated on:
    UK central government planning and spending, 1998–2024; UK central government
    Our recommendation (separate from the research):
    Fill the missing owner, baseline, outcome, budget and milestone fields for every tracked commitment, publish them in the next planning cycle, and report plan completeness and service outcomes separately.
    Strongest counter-evidence:
    Plans continued inside government after 2021 without visible effect; published targets can be gamed and add workload, and publication is not delivery.
    Cost and funding

    Cost completeness: Not yet costed. Funding: Not a direct public-spending programme.

    • Departmental analytical, finance and delivery staff time for published plans (administration; paid by central government): Not yet costed. No grant programme, but existing staff time has an opportunity cost; it is not zero. The NAO does not cost its recommendation.
    Who pays:
    Departments, from administrative budgets: analytical, finance and delivery staff time. There is no grant programme, but the staff time is a real cost.
    Financing proposed:
    A named departmental or Cabinet Office allocation, or an explicit statement of which existing work gives way.
    Gap remaining:
    Staff time not costed — not zero.
    What delivery needs
    Skills:
    Analysts, finance and delivery staff.
    Operational capacity:
    Departmental performance data matched to each commitment.
    Infrastructure:
    A public register of commitments with revision history.
    Permissions:
    None.
    Law:
    None: an administrative decision.
    Public consent:
    Ministers accepting public milestones that may be missed.
    First step and stages

    First step: Complete the missing owner, baseline, outcome, budget and milestone fields for each tracked commitment. (owner: Cabinet Office with each department (UK Facts for its own registry))

    1. Complete the missing fields — Departments; UK Facts for its registry (proposed stage, not an official timetable)
    2. Publish in the next planning cycle — Cabinet Office and HM Treasury (proposed stage, not an official timetable)
    3. Report against stable milestones — Departments, scrutinised by Parliament and the NAO (proposed stage, not an official timetable)

    Depends on: A matching official statistic for each commitment; Funding decisions at fiscal events

    Trade-offs
    Who gains and who loses:
    Voters and Parliament gain information; the cost falls on departmental staff time.
    What else the money or effort could do:
    Analyst and finance time not spent on delivery itself.
    Strongest counterargument:
    Fixed public targets can distort priorities and invite gaming; plans existed internally without improving outcomes.
    Risks:
    Target gaming, bureaucratic workload, and treating publication as delivery.
    How we would judge it
    Baseline:
    Share of tracked commitments with a dated, costed plan (this site’s delivery board).
    Leading indicator:
    Plans published with owner, baseline, budget and milestones for each commitment.
    Outcome:
    Timely service outcomes for each commitment, reported separately from plan completeness.
    Continue, adapt or stop:
    Treat plan completeness as an input only; judge success on measured outcomes, and flag any commitment whose milestones slip without a published explanation.
    Earlier option on this page

    This card replaces the option “Publish a delivery plan for every commitment” (external option: Recommended by the NAO; this site has not found current published plans for the commitments tracked here.). Its evidence: The NAO recommends publishing departmental outcome delivery plans at least annually; plans were produced after the 2020 Spending Review and published in July 2021, but have not been published since (paragraph 1.17). That is an audit judgement, not an evaluation showing plans improve delivery. National Audit Office, Lessons learned: a planning and spending framework that enables long-term value for money (October 2024)

    Sources

    Source published 27 October 2024 (NAO); evidence reviewed 2026-10-04. Reconsider if: The government publishes outcome delivery plans; The Budget confirms or changes funding for tracked commitments; A further NAO report on planning and spending.

    Also on: /manifesto, /politics/parties — one shared record, so its cost is counted once.

  • Action 2A20Policy status: site-editorial action

    Tie spending decisions to realistic outcomes and costs

    Publish the cost of keeping present service standards and the outcome each budget is meant to buy, so reallocations name what is cut and what is gained, then compare forecasts with outturn.

    Assessment (draft, 6 October review)

    • A broad priority including this action (GRP-01): Deliver what is already funded

      Delivery RAG: AmberGate: pending

      Range if completed: 14.0–20.0 out of 30 (equal weights; not yet assessed: expected incremental benefit (Bn), incremental affordability (Co))

      National plan: Growth and prosperity list

    Who decides:
    HM Treasury and departments; Parliament (Estimates) (UK)
    Evidence:
    Expert or audit recommendation. Audit and appraisal guidance recommend the approach; no evaluation shows that it saves a stated sum.
    Expected effect:
    Direction plausible; size not established.
    Cost and funding

    Not yet costed

    Funding: Not yet costed / funding not identified

    Why it is shortlisted here: Several tracked commitments wait on the Budget; realistic costs and outcomes in spending decisions decide whether a plan can be delivered.

    What it takes
    The problem

    Spending decisions are short-term and reactive, and debt interest and borrowing limit choices without saying which spending is least valuable.

    Who is affected, and where

    Users of public services and taxpayers across the UK. Territory: UK. Applies to UK departments; devolved governments set their own budgets within block grants, not assessed here.

    Policy status

    UK Facts proposal. Builds on existing practice: Spending Review 2025 set departmental budgets to 2028–29 and the Green Book (2026) and NAO recommend realistic costs and evaluation. A published “cost of current standards” baseline for each service is a UK Facts proposal.

    The evidence
    What the research found:
    The NAO found a short-term, reactive approach with no cultural shift to long-term value for money, and recommended annual departmental and cross-cutting delivery plans and publication of completed evaluations.
    Evaluated on:
    UK central government spending reviews, 1998–2024; NAO audit synthesis
    Our recommendation (separate from the research):
    Publish service baselines and the cost of maintaining standards before each spending review; name the budget reduced whenever money is reallocated.
    Strongest counter-evidence:
    Planning documents can become paperwork; targets invite gaming; services whose savings are easy to measure may be cut ahead of more valuable ones.
    Cost and funding

    Cost completeness: Not yet costed. Funding: Not yet costed / funding not identified.

    • Analytical and delivery capacity to publish service baselines and outcome measures (administration; paid by central government): Not yet costed. Existing staff time has an opportunity cost. Cash-releasing savings must be shown separately from service improvements.
    Who pays:
    HM Treasury and departments (analytical and delivery staff time).
    Financing proposed:
    None. No automatic savings are assumed; any reprioritisation must name the budget reduced and the service forgone.
    Gap remaining:
    Unknown: analytical capacity has not been costed.
    What delivery needs
    Skills:
    Analysts, evaluators and finance staff.
    Operational capacity:
    Consistent cost and outcome data across departments.
    Infrastructure:
    None beyond data systems.
    Permissions:
    None.
    Law:
    None required.
    Public consent:
    Ministers accepting published trade-offs.
    First step and stages

    First step: Publish consistent baselines and the cost of maintaining present service standards for the next planning cycle. (owner: HM Treasury)

    1. Agree service baselines and outcome measures — HM Treasury and departments (proposed stage, not an official timetable)
    2. Use them in the next spending review — HM Treasury (proposed stage, not an official timetable)
    3. Compare forecasts with outturn each year without rewriting the baseline — HM Treasury; NAO (proposed stage, not an official timetable)

    Depends on: A47: one ledger of costs and funding; Departmental evaluation capacity

    Trade-offs
    Who gains and who loses:
    Services with weak outcome data risk losing out; users of high-value but hard-to-measure services need protection.
    What else the money or effort could do:
    Analytical time spent on baselines is not spent on policy development.
    Strongest counterargument:
    Spending choices are political; better data cannot settle which outcomes matter most.
    Risks:
    Gaming, optimistic assumptions and cutting what is easy to measure.
    How we would judge it
    Baseline:
    Debt interest £108.9bn and borrowing £134.3bn in 2025–26 (OBR databank).
    Leading indicator:
    Share of departmental budgets with published baselines and outcome measures.
    Outcome:
    Forecast-versus-outturn gaps in cost and outcomes; maintenance backlogs.
    Continue, adapt or stop:
    Review if published baselines are not used in allocation decisions within one spending review.
    Sources

    Source published October 2024 (NAO); February 2026 (Green Book); evidence reviewed 2026-10-04. Reconsider if: The next spending review; New NAO work on spending frameworks.

    Also on: Public finances — one shared record, so its cost is counted once.

Decision brief

  • Put every government commitment on a triage board: next decision, whose desk, what money is missing

The leading option set out as a decision someone could take: who decides, who benefits, the best evidence, cost and funding, and the main trade-off. The full research record is one click away.

Decision briefStatutory/accountability reformReviewed 2026-10-04

Put every government commitment on a triage board: next decision, whose desk, what money is missing

Decision required
The Cabinet Office publishes, and updates after each fiscal event, one line per commitment: the promised date, the current stage, the decision now blocking progress, the institution that must take it, the next official evidence release and the funding gap.
Who and where
Voters, Parliament and the users of the services each commitment affects. Applies in: UK.
Accountable body
Cabinet Office (with HM Treasury for funding status)
Intervention
Name, for each commitment, the decision that is blocking it and the institution that must take it.
Best evidence, and where it applies
The NAO recommends publishing outcome delivery plans at least annually; departments last published them in July 2021.Studied in: UK central government departments (UK spending frameworks 1998–2024).
Extra cost of this change
Capital: none identified in the brief.Recurring: Departmental and Cabinet Office staff time to maintain the board — Not yet costed.
Funding
Mainly a legal or regulatory change: administration costs still need a budget.Committed to this change: none.Possible source, not an award: none identified.Unfunded: Staff time is not costed — which does not make it free.
Savings and wider benefits
Not yet specified: no cashable saving or avoided cost has been costed for this change. Expected outcomes are listed one by one in the research appendix and are never added together or counted as money available.
First 90-day step
This site adds the blocking-decision, institution, evidence-release and funding-gap fields to its own board; the government is asked to publish the same fields after the 28 October 2026 BudgetThe proposed first milestone; a 90-day date is not yet specified. Owner: UK Facts (site board); Cabinet Office (official board). Proposed by UK Facts, not an official deadline.
Twelve-month milestone
Not yet specified.Time to a first useful result: The site version immediately; the first official version after the Budget if the Cabinet Office agrees.
Outcome, and when to scale or stop
Measure: Share of commitments with all six fields filled from an official source.Scale if: Blocking decisions are named and then taken, and revisions are dated and explained.Stop if: The board is published but used to redefine commitments without explanation — then the site keeps the original wording and records each change.
Main trade-off
Naming the blocking decision and the money gap exposes ministers to criticism earlier; keeping it internal has not produced visible accountability since 2021.

An editorial proposal by UK Facts for discussion, not government policy. Records: A37 · costs C-A37-ANALYSTS

Research appendix: study design, effect sizes and limits, alternatives, full costing, international comparisons and how we would know

1.The change, in plain words

Put every government commitment on a triage board: next decision, whose desk, what money is missing

2.The decision requested

Decision
Publish a delivery-triage board for the government’s tracked commitments with six fixed fields — promised date, stage, blocking decision, accountable institution, next evidence release, funding gap — first after the 28 October 2026 Budget and then after each fiscal event.
Accountable institution
Cabinet Office (with HM Treasury for funding status)
Geography
UK
Powers
Existing ministerial authority over government publications; no legislation needed. Select committees can request the information.
Delivery partners
HM Treasury; Responsible departments; ONS and departmental statisticians (matching evidence releases); Commons Public Administration and Constitutional Affairs Committee

3.Who it is for, and what changes beyond today

Target population
Voters, Parliament and the users of the services each commitment affects.
Eligibility
The 12 commitments this site tracks since 20 July 2026; the same fields can be applied to any government commitment.
Scale
12 commitments now; any new commitment is added with a start date so it is never shown as late before its own deadline.
Baseline
Site assessment (3 October 2026): 6 of 12 commitments have a dated, costed plan; 3 of those still await funding or legislation; 1 of 12 are in force; 0 of 12 have a measured result; 8 have a dated next step and 4 have none. No official board exists; outcome delivery plans were last published in July 2021.

Source: Prime Minister’s Office (gov.uk), First speech as Prime Minister (20 July 2026) (Commitments as announced; stages assessed by UK Facts); National Audit Office, Lessons learned: a planning and spending framework that enables long-term value for money (HC 234, Session 2024-25) (Paragraph 1.17 (printed p.18))

Change beyond existing law or funding
The site’s board already records plan, authority, delivery and outcome. The change adds the two fields that turn a status into a decision — the blocking decision and the institution that must take it — plus the funding gap and the next evidence release, and asks government to publish the same fields officially.

4.How it would work

Do: Name, for each commitment, the decision that is blocking it and the institution that must take it Changing: so that scrutiny and fiscal events address specific decisions (a Budget allocation, a statutory instrument, a design choice) instead of general progress

  • Commitments with a named blocking decision and accountable institution

    Hypothesis to test

    An accountability output measured on the board itself; not evidence of delivery.

  • Shorter time from a commitment being stuck to the blocking decision being taken

    Hypothesis to test

    No evaluation shows that published boards speed decisions; to be measured by comparing time in each stage before and after publication.

Outcomes are kept separate and never added into one impact figure.

5.Best evidence

  • Lessons learned: a planning and spending framework that enables long-term value for money (HC 234, Session 2024-25)

    Author or institution:
    National Audit Office
    Published:
    October 2024
    Evaluation period:
    UK spending frameworks 1998–2024
    Design:
    Audit synthesis
    Sample or population:
    UK central government departments
    Effect and uncertainty:
    Recommends publishing departmental outcome delivery plans and cross-cutting mission plans at least annually; finds outcome delivery plans not published since July 2021 and government “prone to under-estimate on costs and over-promise on outcomes”.
    Limits:
    An audit recommendation without an outcome evaluation; plans continued internally after 2021.

    Where: Summary paragraph 11, recommendation (a) (printed p.9); paragraphs 1.17 and 2.52. Affiliation is provenance, not proof of quality.

6.Alternatives, counter-evidence and who loses

Closest feasible alternative
Revive annual departmental outcome delivery plans as the NAO recommends, without a commitment-level board.
Strongest counter-evidence
Plans were used inside government after 2021 without visible effect; published targets can be gamed and add workload, and publication is not delivery.

Source: National Audit Office, Lessons learned: a planning and spending framework that enables long-term value for money (HC 234, Session 2024-25) (Paragraph 1.17 (printed p.18))

Distributional effects
None directly; it changes who can see delivery problems, not who receives services.
Main downside
A board that names blocking decisions can become a list of excuses, or push departments to make fewer, vaguer commitments.

The options compared, including current policy

  • The proposal

    Delivery-triage board: promised date, stage, blocking decision, institution, next evidence, funding gap

    Who is reached
    12 tracked commitments; Parliament and voters
    Evidence
    NAO recommendation; site board already records four stages
    Likely outcome and timing
    Site version now; official version after the Budget if agreed
    Cost and funding
    Staff time, not costed; existing budgets
    Main trade-off
    Earlier exposure of stuck commitments
  • Current policy

    Current position: no official board; site tracks four stages

    Who is reached
    Readers of this site
    Evidence
    Plans last published July 2021
    Likely outcome and timing
    No official change
    Cost and funding
    None beyond site time
    Main trade-off
    Whose desk a decision sits on is not visible
  • Alternative

    Revive annual departmental outcome delivery plans only

    Who is reached
    All departments
    Evidence
    NAO recommendation; produced 2020–21
    Likely outcome and timing
    Annual, not tied to each commitment
    Cost and funding
    Departmental staff time
    Main trade-off
    Less specific about the next decision

7.What other countries or the devolved nations show

No comparable evaluation found.

Searched: Evaluations of central delivery units and published delivery trackers: the Inter-American Development Bank’s 2018 study of delivery units in 14 Latin American and Caribbean governments (qualitative case studies; it attributes no result causally to a delivery unit and notes there are no impact evaluations); Institute for Government case studies of the UK Prime Minister’s Delivery Unit (qualitative); and the England–Scotland comparison of NHS waiting-time targets, which evaluates the targets regime rather than a delivery board.

Next step: Treat the board as an accountability tool: record time in each stage before and after publication, and compare commitments with and without an official entry.

8.What delivery needs first

  • data — A matching official measure and next release date for each commitment. (Requirement; owner: Departments and their statisticians)
  • dependency — HM Treasury confirms funding status at each fiscal event; the funding-gap field cannot be filled without it. (Genuine veto: nothing proceeds without it; owner: HM Treasury)
  • staff — Analysts in each department to keep the fields current. (Scarce resource shared with other priorities; owner: Responsible departments)

9.What it would cost

How the cost is built up: Staff time per commitment × commitments × updates a year, plus Cabinet Office coordination. No programme spending.

  • Departmental and Cabinet Office staff time to maintain the board

    Each department with tracked commitments, plus Cabinet Office and HM Treasury coordination

    Not yet costed (ledger C-A37-ANALYSTS)

    recurring; price year not stated; Each fiscal event; Not yet established

10.Who pays, and what is missing

Programme envelope (a possible route, not an award)
None identified
Allocation committed to this change
None
Remaining gap
Staff time is not costed — which does not make it free.
Proposed financing
Existing Cabinet Office and departmental administration budgets, or a statement of which existing reporting gives way.
Responsible payer
central government
Budget displaced
Analytical and private-office time otherwise spent on internal reporting.

11.First milestone and time to a useful result

This site adds the blocking-decision, institution, evidence-release and funding-gap fields to its own board; the government is asked to publish the same fields after the 28 October 2026 Budget (Owner: UK Facts (site board); Cabinet Office (official board). Proposed by UK Facts, not an official deadline.)

Time to first useful result: The site version immediately; the first official version after the Budget if the Cabinet Office agrees.

What could delay it: The government declines to publish Funding decisions are deferred beyond the Budget Commitments are reworded, breaking continuity

12.How we would know

Baseline
6 of 12 with a dated, costed plan; 8 with a dated next step (3 October 2026).
Comparison
Time each commitment spends in each stage before and after the board is published; commitments with and without an official entry.
Leading indicator
Share of commitments with all six fields filled from an official source.
Follow-up
After each fiscal event and each matching statistical release.
Continue if
Blocking decisions are named and then taken, and revisions are dated and explained.
Adapt if
Fields are filled but stay unchanged for successive updates: the board should then show how long each decision has been outstanding.
Stop if
The board is published but used to redefine commitments without explanation — then the site keeps the original wording and records each change.
Thresholds
Not yet set: No business case or evaluation design sets a numerical target for time in stage; set one only after a baseline year of board data.

What is not yet known, and how to find out

  • What it costs departments to keep the board current (cost)Next step: Use the staffing of the 2020–21 outcome delivery plans as a benchmark and ask the Cabinet Office for it.Scope: All tracked commitments, each fiscal event · Data or quotes needed: Staff hours for the 2021 plans · Who can estimate it: Cabinet Office
  • Whether a published board speeds up blocking decisions (effect)Next step: Measure time in stage for a year before and after publication.Defensible route: evaluation of existing delivery
  • Whether the current government runs a central delivery unit (data)Next step: Check a government statement or organisation chart before naming an owner beyond the Cabinet Office.

Sources last checked 4 October 2026 · Owner: Evidence editor (James Harris) · Next check: the first trigger: A change to the government’s missions, plan for change or performance reporting.

More decision briefs on other pages

What it would take

The order things have to happen in, who pays, and the effects and appraisals on record.

The order things have to happen in

  1. First, the prerequisite

    Fill missing owner, baseline, budget, milestone and measure fields for each tracked commitment

    Owner: Departments with the Cabinet Office; UK Facts for its registry

    No date: the timing depends on the steps before it.

  2. Then, the decision

    Confirm or decline funding for tracked commitments at the Budget

    Owner: HM Treasury

    28 October 2026 (Budget) — source

  3. Then, delivery

    Publish delivery plans in the next planning cycle and report against stable milestones

    Owner: Cabinet Office, HM Treasury and departments

    No date: the timing depends on the steps before it.

  4. Finally, the measured outcome

    Measured results for each commitment, reported separately from plan completeness

    Owner: Departments; scrutiny by Parliament and the NAO

    No date: the timing depends on the steps before it.

Who pays, and what is still missing

Cost, committed funding and the remaining gap for the same scope and years. A programme envelope is not an award to a project; a proposal is not committed money. None of these costs has been established yet, so no total is shown.

Cost and funding ledger

  • Departmental analytical, finance and delivery staff time for published plans

    A37 · administration · not costed

    Amount
    Not yet costed
    Who pays
    central government
    Committed
    None identified
    Proposed, not committed
    —
    Gap
    Not established
  • Analytical and delivery capacity to publish service baselines and outcome measures

    A20 · administration · not costed

    Amount
    Not yet costed
    Who pays
    central government
    Committed
    None identified
    Proposed, not committed
    —
    Gap
    Not established

“Not yet costed” means no defensible cost has been found — not that the action is free. Lifetime benefits, benefit-cost ratios and forecast savings are never shown here as money available to spend.

What the evidence says each action changes

No effect has been established for these actions yet: direction plausible; size not established.

How we would know

Tracked commitments with a dated, costed delivery plan; Tracked commitments with a dated next milestone; Tracked commitments with a measured public outcome.

The outcome measures to watch. A baseline is where we start, not a target; where there is no official target we say so.

  • Tracked commitments with a dated, costed delivery plan

    commitments · UK government

    Baseline
    Not published
    Latest
    6 of 12
    3 October 2026

    Proposed ambition (UK Facts, not official): every tracked commitment (12) — a proposed ambition, not an official target

    Source: Prime Minister’s Office (gov.uk), First speech as Prime Minister (20 July 2026) (Commitments as announced; plans assessed by UK Facts on this page’s delivery board). Next release: when any commitment’s plan, funding or status changes (check the release calendar).

  • Tracked commitments with a dated next milestone

    commitments · UK government

    Baseline
    Not published
    Latest
    8 of 12
    3 October 2026

    Target: none — shown to track plan completeness; not a target in itself.

    Source: Prime Minister’s Office (gov.uk), First speech as Prime Minister (20 July 2026) (Milestones listed on this page, each from its government source). Next release: when any commitment’s plan, funding or status changes (check the release calendar).

  • Tracked commitments with a measured public outcome

    commitments · UK government

    Baseline
    Not published
    Latest
    0 of 12
    3 October 2026

    Target: none — too soon: most official outcome data still describe the period before July 2026.

    Source: Prime Minister’s Office (gov.uk), First speech as Prime Minister (20 July 2026) (Outcome stage assessed by UK Facts against official statistics). Next release: as official statistics covering the period after July 2026 are published (check the release calendar).

Where the ideas come from

Research, counter-evidence and methods (3 sources; 3 claims held back)

Counter-evidence and criticism

  • Give every commitment an owner, budget and measurable result: Plans continued inside government after 2021 without visible effect; published targets can be gamed and add workload, and publication is not delivery. (National Audit Office)
  • Tie spending decisions to realistic outcomes and costs: Planning documents can become paperwork; targets invite gaming; services whose savings are easy to measure may be cut ahead of more valuable ones. (National Audit Office)

Claims held back

  • That publishing delivery plans improves delivery — The NAO recommends publication for accountability; it does not show an effect on outcomes, and plans were kept internally after 2021. Needed: An evaluation comparing published and unpublished plans.
  • Whether the current government runs a central delivery unit — Not confirmed from a primary source for this review. Needed: A government statement or organisation chart.
  • Whether the five missions and the Plan for Change milestones still stand under the Burnham government — The GOV.UK missions hub was removed on 5 August 2026, but the Plan for Change paper (December 2024) is still published and no statement keeping, changing or dropping the missions or milestones was found on 4 October 2026. Individual milestones have been restated separately (1.5 million homes, 25 August 2026). The Prime Minister’s first speech promised a new ten-year plan “later this year”; none had been published by 4 October 2026. Needed: The promised ten-year plan, or a government statement on the missions and milestones.

“Full text checked” means we read the report itself; “relevant passages” means the sections behind each figure; “summary or abstract only” means we could not read the full study, so no number from it is published here without another source.

Other options compared — not on the shortlist (3)

Other options compared

Options from earlier work on this page that are not on the shortlist. They remain valid choices; their evidence is shown as before.

  • preventionStatus: operating

    Independent costing of every tax and spending pledge

    Aims to:
    The cost of each measure is tested before it is relied on, so pledges are not announced with figures that later change.
    How:
    The OBR scrutinises the government’s draft costings of tax and spending measures before each fiscal event and says whether it endorses them as reasonable central estimates.
    Who decides:
    HM Treasury (costings) and the Office for Budget Responsibility (scrutiny).
    Main constraint:
    Measures announced between fiscal events are costed only when they reach one.
    Evidence:
    Moderate evidence — evaluated, with limits on scope or transfer
    See the trade-offs and evidence
    What the evidence shows
    OBR certification is an established, published process at every fiscal event. It tests the cost estimate, not whether a measure is delivered or works.
    Policy status
    Applies to measures announced at fiscal events; the electricity VAT cut and pubs relief are due to be scored at the Budget on 28 October 2026.
    Resources
    OBR and Treasury analysts.
    Consent and decisions needed
    Already in law (Budget Responsibility and National Audit Act 2011).
    Time
    At each fiscal event.
    Cost and yield
    Within existing OBR and Treasury budgets.
    Trade-offs and who pays
    Waiting for a fiscal event can delay announcements; costings carry uncertainty the OBR itself rates.
    How we would know it worked
    Leading indicator: Share of tracked funded commitments with an OBR-certified costing. Outcome: Smaller revisions between announced and final costs. It would not be working if: Certified costings are repeatedly revised by large amounts after delivery.
  • capacityStatus: external option

    A small central unit tracking a few priorities

    Aims to:
    Problems in delivery are spotted and escalated early, before deadlines pass.
    How:
    A unit close to the Prime Minister tracks a handful of priorities with regular data and stock-takes, and escalates blockages to ministers.
    Who decides:
    Prime Minister’s Office and Cabinet Office.
    Main constraint:
    Needs sustained prime-ministerial attention; too many priorities dilute it.
    Evidence:
    Limited evidence — plausible mechanism, little direct evaluation
    See the trade-offs and evidence
    What the evidence shows
    The Institute for Government found a mixed record internationally: several delivery units closed after failing to meet expectations. Success depended on visible political backing and a tightly defined remit.
    Policy status
    This site has not confirmed whether the current government runs such a unit.
    Resources
    A small team of analysts and officials; departmental data.
    Consent and decisions needed
    An administrative decision.
    Time
    Months to set up; value depends on years of consistent use.
    Cost and yield
    No official costing; staff costs only.
    Trade-offs and who pays
    Central pressure can crowd out local judgement and favour measurable targets.
    How we would know it worked
    Leading indicator: Regular published progress reports on named priorities. Outcome: More priority milestones met on time. It would not be working if: Milestones slip at the same rate as before the unit existed.
  • preventionStatus: operating

    Publish the statistic that matches each pledge

    Aims to:
    Every pledge can be judged on the measure it actually promised, not a proxy.
    How:
    Departments publish, and cite, the specific official measure each pledge depends on — for example additional elective activity for an appointments pledge, or neighbourhood officer numbers for a policing pledge — in line with the statistics regulator’s transparency guidance.
    Who decides:
    Departments and their heads of profession for statistics; Office for Statistics Regulation (oversight).
    Main constraint:
    Some outcomes take years to measure, and new collections need time to become reliable.
    Evidence:
    Not evaluated — a mechanism to test, not an evidenced fix
    See the trade-offs and evidence
    What the evidence shows
    The Office for Statistics Regulation asks that figures used by ministers be published, sourced and explained. Whether matching statistics improve delivery has not been evaluated.
    Policy status
    The guidance exists; several tracked pledges still have no matching published series.
    Resources
    Statistical staff; sometimes new data collection.
    Consent and decisions needed
    Administrative; no legislation needed.
    Time
    Months for existing data; a year or more for new collections.
    Cost and yield
    No official costing.
    Trade-offs and who pays
    New measures can break comparisons with older series.
    How we would know it worked
    Leading indicator: Share of tracked pledges with a matching published measure. Outcome: Fewer pledges that “cannot be assessed”. It would not be working if: Matching measures exist but ministers continue to cite proxies.
The options side by side
OptionResourcesTimeEvidenceOutcome to watch
Independent costing of every tax and spending pledgeOBR and Treasury analysts.At each fiscal event.moderateSmaller revisions between announced and final costs.
A small central unit tracking a few prioritiesA small team of analysts and officials; departmental data.Months to set up; value depends on years of consistent use.limitedMore priority milestones met on time.
Publish the statistic that matches each pledgeStatistical staff; sometimes new data collection.Months for existing data; a year or more for new collections.not evaluatedFewer pledges that “cannot be assessed”.

Plan reviewed 2026-10-04. How we judge evidence.

How this connects

Sources and methods (11)

Method notes

  • Selection: the government’s own headline commitments announced since 20 July 2026, as recorded in the registry. It is not the whole programme; the inherited 2024 manifesto is tracked on /manifesto.
  • Dated, costed plan: a delivery date, a stated cost (or a regulatory change with no spending cost) and a named delivery mechanism have all been published. An estimate counts as a cost; funding confirmation is assessed separately as “authority”.
  • Stages are assessed independently and can run in parallel; “not applicable” is used where a stage does not apply.
  • Each entry shows the date it was last checked against its source. Entries not re-checked since 11 August 2026 may lag later announcements.
  • An outcome is marked measured only when a commitment has a defined measure and an official result published after delivery began. A change in a national statistic after July 2026 is not attributed to this government by itself.